ERER Project Revised





Project Start:
Project Finish:
Mon 10/22/01
Thu 1/30/03


Tasks


IDTask NameDurationStartFinishResource Names% Complete
1
Project Management
321 daysMon 10/22/01Thu 1/30/03 28%
2
Pre-Implementation
14 daysMon 10/22/01Thu 11/8/01 100%
3
Detailed Scope / Deliverable definition
5 daysMon 10/22/01Fri 10/26/01 100%
4
Complete Work Breakdown Structure
1 dayMon 10/22/01Mon 10/22/01 100%
5
Analyze / document risks
5 daysMon 10/29/01Fri 11/2/01 100%
6
Define project team / organization chart
1 dayTue 10/30/01Tue 10/30/01 100%
7
Deploy change control policy / processes
1 dayThu 11/8/01Thu 11/8/01 100%
8
Deploy risk management policy / processes
1 dayThu 11/8/01Thu 11/8/01 100%
9
Project Initiation - Milestone
1 dayThu 11/8/01Thu 11/8/01 100%
10
Project status reporting
321 daysMon 10/22/01Thu 1/30/03 28%
11
Weekly reports to Chair and Vice Chair of Task Force and to LCC
321 daysMon 10/22/01Thu 1/30/03 30%
12
Regular meetings with ERER Task Force to develop and continue project approach / procedures
1 dayMon 10/22/01Mon 10/22/01 30%
13
Application Error and Issues Reporting
321 daysMon 10/22/01Thu 1/30/03 0%
14
Evaluate Project Plan at each phase-end, adjust as needed
321 daysMon 10/22/01Thu 1/30/03 30%
15
Preparation of progress report to legislative sessions 2002 and 2003.
321 daysMon 10/22/01Thu 1/30/03 50%
16
Post Implementation
10 daysMon 1/6/03Fri 1/17/03 0%
17
Create project closure and audit report
10 daysMon 1/6/03Fri 1/17/03 0%
18
Update enhancement and change request list
10 daysMon 1/6/03Fri 1/17/03 0%
19
Update Error / Issue Report
10 daysMon 1/6/03Fri 1/17/03 0%
20
Assessment Phase
146 daysMon 10/22/01Tue 5/21/02 58%
21
Solidify Project Scope
72 daysFri 11/9/01Tue 2/26/02 63%
22
Identify Processes for Pilot Testing
41 daysFri 11/9/01Mon 1/14/02 0%
23
Identify documents and processes desired for pilot
41 daysFri 11/9/01Mon 1/14/02 0%
24
Identify Public and Private Involvement
41 daysMon 11/19/01Tue 1/22/02 90%
25
Identify public groups (including Recorder, Auditor and Treasurer)
41 daysMon 11/19/01Tue 1/22/02 100%
26
Identify Private groups (including title companies, mortgage companies, banks)
41 daysMon 11/19/01Tue 1/22/02 100%
27
Identify education / communication plan to educate parties on involvement
41 daysMon 11/19/01Tue 1/22/02 100%
28
Identify legislative needs to facilitate envelopment
41 daysMon 11/19/01Tue 1/22/02 60%
29
Identify Pilot Counties
27 daysMon 1/21/02Tue 2/26/02 0%
30
Identify Pilot Parameters (Document volumes, document types, technology requirements, etc)..
27 daysMon 1/21/02Tue 2/26/02 0%
31
Scope complete milestone
1 dayMon 1/21/02Mon 1/21/02 0%
32
Create Project Sub-Committees
34 daysMon 10/22/01Mon 12/10/01 100%
33
Identify sub-committee needs
1 dayMon 10/22/01Mon 10/22/01 100%
34
Solicit membership
24 daysMon 10/22/01Mon 11/26/01 100%
35
Appoint committee chair
34 daysMon 10/22/01Mon 12/10/01 100%
36
Detail work process and needs for committees
34 daysMon 10/22/01Mon 12/10/01 100%
37
Sub-Committee milestone
34 daysMon 10/22/01Mon 12/10/01 100%
38
Select Consulting Teams - RFPs
42 daysThu 11/8/01Mon 1/14/02 100%
39
Develop consultant RFP
5 daysThu 11/8/01Wed 11/14/01 100%
40
Publish RFP
7 daysTue 11/13/01Fri 11/23/01 100%
41
Review consultant proposals
18 daysMon 11/26/01Wed 12/19/01 100%
42
Select consultant
1 dayMon 1/7/02Mon 1/7/02 100%
43
Consultant team selection - Milestone
1 dayMon 1/14/02Mon 1/14/02 100%
44
Prepare Interview Template
5 daysMon 1/14/02Fri 1/18/02Interview Consultant I,Interview Consultant II100%
45
ID Content and Format Questions
5 daysMon 1/14/02Fri 1/18/02 100%
46
ID Index questions
5 daysMon 1/14/02Fri 1/18/02 100%
47
ID Technology Feature, e-Management and e-Processing Standards
5 daysMon 1/14/02Fri 1/18/02 100%
48
ID e-Recording Payment Information
5 daysMon 1/14/02Fri 1/18/02 100%
49
Document Interview Template
5 daysMon 1/14/02Fri 1/18/02 100%
50
Template Milestone
1 dayFri 1/18/02Fri 1/18/02 100%
51
Conduct Task Force Interviews
25 daysMon 1/21/02Fri 2/22/02Technology Consultant I,Standards Consultant II,Legal Research[35%],Technical Design[35%]80%
52
Task Force Concerns List
19 daysMon 1/21/02Thu 2/14/02 80%
53
Indexes, features, content, format, authenticating, securing, record prioritizing
19 daysMon 1/21/02Thu 2/14/02 80%
54
Technology Assessment at County and Private Sector Offices
19 daysMon 1/21/02Thu 2/14/02 80%
55
Evaluate documentation detailing current technology and transaction volumes at the county and private sector offices
19 daysMon 1/21/02Thu 2/14/02 80%
56
Document the current state of technology, and transaction volumes at each county and private sector office
19 daysMon 1/21/02Thu 2/14/02 80%
57
Evaluate archive and retrieval needs and issues
19 daysMon 1/21/02Thu 2/14/02 80%
58
Assess infrastructure needs and concerns
19 daysMon 1/21/02Thu 2/14/02 80%
59
Functional and Business Process Assessment at County and Private Sector offices
19 daysMon 1/21/02Thu 2/14/02 80%
60
Document the current state of processes at each county and private sector office
19 daysMon 1/21/02Thu 2/14/02 80%
61
Evaluate documentation detailing current processes at the county and private sector offices
19 daysMon 1/21/02Thu 2/14/02 80%
62
Assess the electronic recording systems used in other jurisdictions
19 daysMon 1/21/02Thu 2/14/02 80%
63
Evaluate any national standards for electronic document management
19 daysMon 1/21/02Thu 2/14/02 80%
64
Identify best practices from aggregate county and private sector offices and national information
19 daysMon 1/21/02Thu 2/14/02 80%
65
Identify legal requirements
19 daysMon 1/21/02Thu 2/14/02 80%
66
Identify business processes, workflow, automated processes, and operational needs
19 daysMon 1/21/02Thu 2/14/02 80%
67
Identify functionality requirements necessary for a successful pilot implementation
19 daysMon 1/21/02Thu 2/14/02 80%
68
Mid-Assessment Review - Milestone
1 dayThu 2/14/02Thu 2/14/02 80%
69
Data / Security Requirements
19 daysMon 1/21/02Thu 2/14/02 80%
70
Identify data security needs
19 daysMon 1/21/02Thu 2/14/02 80%
71
Identify legacy data migration needs and data cleansing issues
19 daysMon 1/21/02Thu 2/14/02 80%
72
Report Needs
19 daysMon 1/21/02Thu 2/14/02 80%
73
Identify reporting needs / requirement for county and private sector offices
19 daysMon 1/21/02Thu 2/14/02 80%
74
Wrap-up of Interviews
5 daysMon 2/18/02Fri 2/22/02 80%
75
Task Force Interview Completion Milestone
1 dayFri 2/22/02Fri 2/22/02 0%
76
Conduct Survey of All Other Counties
39 daysMon 1/21/02Thu 3/14/02 6%
77
Overveiw of training agenda for survey staff (interns)
2 daysMon 1/21/02Tue 1/22/02 100%
78
Draft survey script for interns
3 daysMon 2/4/02Wed 2/6/02 0%
79
Conduct surveys via phone or on-site visits by interns
25 daysThu 2/7/02Wed 3/13/02 0%
80
Summarize responses
1 dayThu 3/14/02Thu 3/14/02 0%
81
Vendor Selection Process
41 daysMon 2/4/02Mon 4/1/02 19%
82
Identify E-Signature Vendors
10 daysMon 2/4/02Fri 2/15/02 50%
83
Identify E-Recording Software Vendors
10 daysMon 2/4/02Fri 2/15/02 50%
84
Create functionality scripts based on needs identified in assessment
10 daysMon 2/18/02Fri 3/1/02 0%
85
Obtain Task Force approval of script
1 dayMon 3/4/02Mon 3/4/02 0%
86
Communicate script to vendor group
1 dayTue 3/5/02Tue 3/5/02 0%
87
Schedule evaluation demos for Task Force based on scripts
11 daysWed 3/6/02Wed 3/20/02 0%
88
Conduct question and answer series
3 daysThu 3/21/02Mon 3/25/02 0%
89
Select vendor best matching requirements and needs
1 dayTue 3/26/02Tue 3/26/02 0%
90
Finalize vendor negotiations directed at application pricing, availability requirements, customization and bug fix, overall support response time / service level agreements
4 daysWed 3/27/02Mon 4/1/02 0%
91
Vendor Selection - Milestone
1 dayMon 4/1/02Mon 4/1/02 0%
92
Prepare and Present Standards
80 daysMon 1/28/02Fri 5/17/02 0%
93
Review Other States' Processes
35 daysMon 1/28/02Fri 3/15/02 0%
94
Standard Review: Electronic Recording Technology Features
25 daysMon 2/25/02Fri 3/29/02Technology Consultant I,Standards Consultant II0%
95
Assess interview findings against Considerations 11 through 18
5 daysMon 2/25/02Fri 3/1/02 0%
96
Conduct additional research
15 daysMon 3/4/02Fri 3/22/02 0%
97
Document recommendations for technology features
5 daysMon 3/25/02Fri 3/29/02 0%
98
Standards Review: Real Estate Record Indexing
15 daysMon 4/29/02Fri 5/17/02Legal Research[35%],Standards Consultant II0%
99
Assess interview findings against Considerations 19 through 21
5 daysMon 4/29/02Fri 5/3/02 0%
100
Conduct additional research
5 daysMon 5/6/02Fri 5/10/02 0%
101
Document recommendations for technology features
5 daysMon 5/13/02Fri 5/17/02 0%
102
Standards Review: Content and Format
15 daysMon 4/29/02Fri 5/17/02Standards Consultant II,Technical Design[35%]0%
103
Assess interview findings against Considerations 22 through 26
5 daysMon 4/29/02Fri 5/3/02 0%
104
Conduct additional research
5 daysMon 5/6/02Fri 5/10/02 0%
105
Document recommendations for technology features
5 daysMon 5/13/02Fri 5/17/02 0%
106
Standards Review: Authentication, Securing, Record Priority
15 daysMon 4/29/02Fri 5/17/02Standards Consultant II,Legal Research[35%]0%
107
Assess interview findings against Considerations 27 through 30
5 daysMon 4/29/02Fri 5/3/02 0%
108
Conduct additional research
5 daysMon 5/6/02Fri 5/10/02 0%
109
Document recommendations for technology features
5 daysMon 5/13/02Fri 5/17/02 0%
110
ERER Payment Methods
15 daysMon 4/29/02Fri 5/17/02Standards Consultant II0%
111
Assess Considerations 31 through 37
5 daysMon 4/29/02Fri 5/3/02 0%
112
Conduct additional research
5 daysMon 5/6/02Fri 5/10/02 0%
113
Document recommendations for technology features
5 daysMon 5/13/02Fri 5/17/02 0%
114
Business Process / Redesign
15 daysMon 4/29/02Fri 5/17/02Standards Consultant I,Standards Consultant II0%
115
Assess county processes
5 daysMon 4/29/02Fri 5/3/02 0%
116
Identify redundancy, non-value add processes, etc
10 daysMon 5/6/02Fri 5/17/02 0%
117
Recommend redesign and process streamlines
5 daysMon 4/29/02Fri 5/3/02 0%
118
Draft Models and Standards
35 daysMon 2/25/02Fri 4/12/02 0%
119
Deliver / Recommendation / Baseline Standards
25 daysMon 4/15/02Fri 5/17/02Standards Consultant I,Standards Consultant II0%
120
Meet with ERER Task Force and present standards for authorization
25 daysMon 4/15/02Fri 5/17/02 0%
121
Phase End Review
2 daysMon 5/20/02Tue 5/21/02 0%
122
Conduct walkthrough of assessment findings
1 dayMon 5/20/02Mon 5/20/02 0%
123
Assessment - Phase End Milestone
1 dayTue 5/21/02Tue 5/21/02 0%
124
Design Phase
129 daysMon 1/7/02Mon 7/8/02 3%
125
Technology GAP Analysis, all counties and application standards
10 daysMon 5/6/02Fri 5/17/02Technology Consultant III0%
126
Identify technology gaps between county pilots offices and private sector and vendor package requirements
10 daysMon 5/6/02Fri 5/17/02 0%
127
Document technology matrix for all county offices and pilot host facility
10 daysMon 5/6/02Fri 5/17/02 0%
128
Pilot Architecture and Dual Mode Processes
10 daysMon 5/20/02Fri 5/31/02Technology Consultant I,Technology Consultant II0%
129
Document scenarios that will allow pilot testing while at the same time allowing county offices to continue business using current technology/process
10 daysMon 5/20/02Fri 5/31/02 0%
130
Configure a development site for creating pilot requirements and hosting
10 daysMon 5/20/02Fri 5/31/02 0%
131
Mid-Design Review - Milestone
1 dayFri 5/31/02Fri 5/31/02 0%
132
Functional and Business Process Design
10 daysMon 6/10/02Fri 6/21/02Technology Consultant IV,Standards Consultant II,Legal Research[35%]0%
133
Identify business functionality gaps between ERER requirements and vendor package functionality
10 daysMon 6/10/02Fri 6/21/02 0%
134
Design functionality requirements identified for pilot
10 daysMon 6/10/02Fri 6/21/02 0%
135
Design workflow model and functionality standards
10 daysMon 6/10/02Fri 6/21/02 0%
136
Define automated processes, calculations and screen pops
10 daysMon 6/10/02Fri 6/21/02 0%
137
Security
5 daysMon 6/3/02Fri 6/7/02Technology Consultant I0%
138
Design database and application security needs
5 daysMon 6/3/02Fri 6/7/02 0%
139
Design web security needs
5 daysMon 6/3/02Fri 6/7/02 0%
140
Communication
5 daysMon 1/7/02Fri 1/11/02 58%
141
Design a communication plan that includes educating all county offices and private sector on operational changes, security standards, training dates, status of pilot implementation progress
5 daysMon 1/7/02Fri 1/11/02 70%
142
Communication - Milestone
1 dayFri 1/11/02Fri 1/11/02 0%
143
Report Design
5 daysMon 6/24/02Fri 6/28/02Technology Consultant II0%
144
Design reports identified for pilot
5 daysMon 6/24/02Fri 6/28/02 0%
145
Implementation Plan
5 daysMon 6/3/02Fri 6/7/02Technology Consultant I0%
146
Document detailed implementation plan for pilot host site and county offices and private sector
5 daysMon 6/3/02Fri 6/7/02 0%
147
Develop communication plan for pilot and full rollout
5 daysMon 6/3/02Fri 6/7/02 0%
148
Develop Backup / Recover Plans
5 daysMon 6/24/02Fri 6/28/02Technology Consultant I0%
149
Document backup and recovery procedures
5 daysMon 6/24/02Fri 6/28/02 0%
150
Define county office support procedures
5 daysMon 6/24/02Fri 6/28/02 0%
151
Phase End Review
6 daysThu 6/27/02Mon 7/8/02 0%
152
Document design
5 daysThu 6/27/02Fri 7/5/02 0%
153
Conduct walkthrough of design
1 dayMon 7/8/02Mon 7/8/02 0%
154
Design - Phase End Milestone
1 dayMon 7/8/02Mon 7/8/02 0%
155
Development Phase
26 daysMon 7/8/02Mon 8/12/02 0%
156
Application Configuration
20 daysMon 7/8/02Fri 8/2/02Technology Consultant I,Technology Consultant II0%
157
Develop a pilot application based on pilot requirements
20 daysMon 7/8/02Fri 8/2/02 0%
158
Unit Testing By ERER Task Force Members
20 daysMon 7/8/02Fri 8/2/02 0%
159
Create test scripts for pilot offices and private sector
1 dayMon 7/8/02Mon 7/8/02 0%
160
Conduct unit testing and modify as needed
20 daysMon 7/8/02Fri 8/2/02 0%
161
Mid-Development Review - Milestone
1 dayFri 8/2/02Fri 8/2/02 0%
162
Report Needs
20 daysMon 7/8/02Fri 8/2/02Technology Consultant I0%
163
Develop reports
20 daysMon 7/8/02Fri 8/2/02 0%
164
Technology Setup / Configuration
5 daysMon 7/29/02Fri 8/2/02Technology Consultant I,Technology Consultant II0%
165
Configure Web Server
5 daysMon 7/29/02Fri 8/2/02 0%
166
Configure database and application servers
5 daysMon 7/29/02Fri 8/2/02 0%
167
Configure pilot workstations
5 daysMon 7/29/02Fri 8/2/02 0%
168
Phase End Review
6 daysMon 8/5/02Mon 8/12/02 0%
169
Document development issues
5 daysMon 8/5/02Fri 8/9/02 0%
170
Conduct walkthrough of developed application
1 dayMon 8/12/02Mon 8/12/02 0%
171
Development - Phase End Milestone
1 dayMon 8/12/02Mon 8/12/02 0%
172
Implementation Phase
38 daysMon 7/1/02Fri 8/23/02 0%
173
Training Program Development
33 daysMon 7/1/02Fri 8/16/02 0%
174
Develop training manuals - End Users and IT Support
2.5 daysMon 7/22/02Wed 7/24/02Standards Consultant II,Technology Consultant I0%
175
Schedule training
1 dayMon 7/1/02Mon 7/1/02 0%
176
Train pilot user group
5 daysMon 8/12/02Fri 8/16/02Standards Consultant II0%
177
Install - Final Configuration and Production Database Build
5 daysMon 8/12/02Fri 8/16/02Technology Consultant I,Technology Consultant II,Technology Consultant III,Technology Consultant IV0%
178
Install client software and connectivity
5 daysMon 8/12/02Fri 8/16/02 0%
179
Install host environment
5 daysMon 8/12/02Fri 8/16/02 0%
180
Set-up Business Rules
5 daysMon 8/12/02Fri 8/16/02 0%
181
Phase End Review
5 daysMon 8/19/02Fri 8/23/02 0%
182
Document Implementation plan
5 daysMon 8/19/02Fri 8/23/02 0%
183
Conduct walkthrough of Pilot application with Task Force
1 dayFri 8/23/02Fri 8/23/02 0%
184
Implementation – Phase End Milestone
1 dayFri 8/23/02Fri 8/23/02 0%
185
Pilot Testing Program
106 daysMon 8/12/02Mon 1/13/03 0%
186
Pilot Testing Process
96 daysMon 8/19/02Mon 1/6/03 0%
187
Perform stress, load and capacity tests to ensure county and private sector offices and host client pass usability standards
96 daysMon 8/19/02Mon 1/6/03 0%
188
Test accessibility of pilot application from county offices and private sector
96 daysMon 8/19/02Mon 1/6/03 0%
189
Test application according to testing scripts
96 daysMon 8/19/02Mon 1/6/03 0%
190
Stage One of Pilot - Milestone
1 dayMon 8/19/02Mon 8/19/02 0%
191
Pilot Changes / Enhancements
101 daysMon 8/12/02Mon 1/6/03Pilot Technical Support[15%]0%
192
Document Issues / Needs / Concerns
96 daysMon 8/12/02Mon 12/30/02 0%
193
Evaluate cost / benefit of pilot change
96 daysMon 8/19/02Mon 1/6/03 0%
194
Configure / make approved changes
96 daysMon 8/19/02Mon 1/6/03 0%
195
Pilot Communication Program
96 daysMon 8/19/02Mon 1/6/03 0%
196
Communicate regularly with pilot sites and document findings
96 daysMon 8/19/02Mon 1/6/03 0%
197
Publish findings for all pilot offices to share and initiate additional feedback
96 daysMon 8/19/02Mon 1/6/03 0%
198
Stage Two of Pilot – Milestone
1 dayFri 9/27/02Fri 9/27/02 0%
199
Vendor Communication
96 daysMon 8/19/02Mon 1/6/03 0%
200
Communicate feedback to application vendor with bugs and usability issues
96 daysMon 8/19/02Mon 1/6/03 0%
201
Manage bug fixes
96 daysMon 8/19/02Mon 1/6/03 0%
202
Monitor service and response against service level agreement
96 daysMon 8/19/02Mon 1/6/03 0%
203
Vendor Performance Review - Milestone
1 dayFri 10/25/02Fri 10/25/02 0%
204
Phase End Review
52 daysFri 10/25/02Mon 1/13/03 0%
205
Document pilot testing issues
15 daysFri 10/25/02Thu 11/14/02 0%
206
Pilot Program - Phase End Review
1 dayThu 11/14/02Thu 11/14/02 0%
207
Finalize recommended standards and feature definition
1 dayMon 1/13/03Mon 1/13/03 0%